Trungnam Group inaugurates solar power project

Trungnam Group officially inaugurated the 500KV transformer station and 220/500KV Grid line, and the 450 MW Trung Nam Thuan Nam solar power plant on October 12th, 2020 in Phuoc Minh commune, Thuan Nam district of the south-central Ninh Thuan Province. It's a magnificent event and key project in celebration of the 14th Ninh Thuan provincial Party's Congress, 2021-2025 terms.

Following the proposal, Trungnam Group was approved as an investor of the 500KV transformer station and 220KV/500KV power transmission system, in combined of a 450 MW solar power plant under the document No 831/UBND-KTTH sealed on March 18th, 2020, and the decision for investment proposal No 79/QĐ-UBND on April 3rd, 2020. Trungnam Group promptly completed legal procedures. At the same time, they focus all their resources to complete the project assigned by Ninh Thuan Provincial People's Committee.

With a target of completing the project in 102 days, Trungnam Group had finished the land clearance process in 45 days with the hard-working days from 8,000 laborers and engineers in handing over the project as the proposed time of completion. 

Trungnam Group also greatly contributed to helping the local community as a role and responsibility of a potential investor in Ninh Thuan Province. The Group, in co-operation with the provincial Fatherland Front, Thuan Nam communal people's committee, and provincial association of poor patients, had donated 102 houses worth VND 5.1 billion to poor households in the province during the construction of projects here.

 

500kV substation and 220 / 500kV transmission line combined with Trung Nam Thuan Nam solar power plant 450 MW, in addition to exploiting more than 1 billion kWh, it will make an important contribution to releasing the capacity of the grid for Ninh Thuan and South Central Coast. Two transformer stations of the project, with a total capacity of 1.800MVA and lines designed to improve connectivity, will increase system reliability in the regional power grid.

 


The completion and putting into use of the 500kV transformer station and the 220 / 500kV transmission line in combination with the 450 MW Trung Nam Thuan Nam solar power plant has several important meanings:
- Contribute to the realization of Resolution 115 of the Government making Ninh Thuan become the national renewable energy center.
- Make an important contribution to releasing the capacity of renewable energy plants in Ninh Thuan and Binh Thuan areas, avoiding deflation causing damage to the factories of thousands of billion VND per year, improving the economic environment. 
- Add more than 1 billion kWh of electricity each year to the system, promoting the development of renewable energy to replace other non-renewable sources, especially environmental protection.
- Thoroughly grasp Resolution 55 of the Politburo, promote the development of renewable energy, private participation in source development and construction of transmission infrastructure.

At the same time, Trungnam Group is also the executing unit of the Ca Na Seaport Complex project, Ninh Thuan province. It will have two wharves capable of receiving ships with a deadweight tonnage (DWT) of up to 70,000-100,000, and one wharf handling ships of 20,000DWT by December 2022. When put into operation, the project will make an important contribution to supporting the transport of equipment, especially super-heavy equipment for renewable energy projects and electrification projects in the field of Ninh Thuan province, the South Central region, and the Central Highlands.
 

With the existing advantages in infrastructure, experience in implementing renewable energy projects, and a team of high-quality experts and engineers in the field, Trungnam Group affirms to be a potential investor in implementing large-scale electrification projects in the future./.

 